When we enter Holidays in the Scheduler everything seems to work meaning we can see the day/date in the list however nothing appears to be enter in the actual Schedule.
Ex. Scheduler Options -> click the Holidays... button. Then enter the information, name & date. The information shows in the block to the left. Then close out of Scheduler Options and go the Schedule for that day and there's nothing listed.
Scheduler Options - Holidays
- megoff
- System Guru / Moderator
- Posts: 185
- Joined: Wed Jan 27, 2021 3:31 pm
- Location: San Diego, CA
- Contact:
Re: Scheduler Options - Holidays
Hi Dan,
When it comes to the Scheduler we don't stop anyone from scheduling on any given day, but when it comes to the holidays they are visible in two ways. One the mini calendar the date will be red. This calendar is on the top left of the scheduling tab in the scheduler. The next is that on a week view you're able to see that the day that's a marked as a holiday is grayed out to show the shop is closed, similar to the weekends (if you're closed all weekend). The screenshots below are showing Memorial day as a holiday.
When it comes to the Scheduler we don't stop anyone from scheduling on any given day, but when it comes to the holidays they are visible in two ways. One the mini calendar the date will be red. This calendar is on the top left of the scheduling tab in the scheduler. The next is that on a week view you're able to see that the day that's a marked as a holiday is grayed out to show the shop is closed, similar to the weekends (if you're closed all weekend). The screenshots below are showing Memorial day as a holiday.
M1 Product Manager
-
- 400 Club: Mega-Star Contributor
- Posts: 489
- Joined: Thu Dec 10, 2015 5:19 am
- Location: Glenmoore, PA
- Contact:
Re: Scheduler Options - Holidays
After scheduling Memorial Day as closed 7am-5pm and nothing shows up in the Calendar week/date view. Do you have to choose full day for something to show?
Dan
- megoff
- System Guru / Moderator
- Posts: 185
- Joined: Wed Jan 27, 2021 3:31 pm
- Location: San Diego, CA
- Contact:
Re: Scheduler Options - Holidays
Are you setting as a holiday in the Schedule options or are you just putting an event it saying it's a holiday?